Insider Solutions: Reporting Equipment Changes
What to do when your CMO changes the manufacturing equipment line.


Pharmaceutical Technology
Volume 35, Issue 3, pp. 130-131


Susan J. Schniepp
The pharmaceutical industry has been trying to become more efficient from both manufacturing and regulatory perspectives. The challenge is to improve processes, quality systems, and manufacturing capabilities while operating efficiently and in a manner that ensures safe, effective, and cost-efficient medicines to patients. Many updates to processes and quality systems can be easily and readily implemented with little or no impact on regulatory filings. However, changes to manufacturing equipment do affect submissions.

Consider the following scenario. A contract manufacturing organization (CMO) making aseptic injectable products is planning to update one of its manufacturing lines where multiple products from various clients are made. The equipment involved includes a vial washer, a depyrogenation tunnel, and a filling machine. In addition, a restricted access barrier system (RABS) will be added around the new filling machine and the automatic tray-off area to increase protection against human intervention.

These equipment updates will impact the regulatory filings of the CMO's clients. The affected clients are notified approximately six months prior to when the replacement is scheduled. Clients also are informed of the necessary downtime needed to complete the activities required to ensure that the new line is capable of producing the same quality of product as the previous line equipment.

In this scenario, the question most often posed to the CMO from the client is, "What is the recommended filing strategy for the proposed changes?" To address this question, several points must be considered. One consideration is that the CMO must adjust its production schedule to ensure that the product reamins available in the market during the scheduled downtime. Avoiding a drug shortage is particularly important in situations where the CMO is the sole source of the product.

Another item to consider is how well the CMO understands the client's filing with respect to equipment details. The goal of the CMO in this situation is to be out of commission for the shortest length of time and to propose the most reasonable and acceptable filing strategy to their clients and the appropriate regulatory agency.

In the most conservative case, these changes might be filed as a prior approval supplement (PAS). However, this approach requires regulatory agency approval before work can begin and, as a result, could lead to the manufacturing line being down for several months to a year.

Consider also that the project could take four to six months after approval, including performing the appropriate installation, operational, and performance qualifications and the process validation requirements needed to requalify the new line. In the least conservative case, these changes could be reported to the regulator in the client's annual report filing.


ADVERTISEMENT

blog comments powered by Disqus
LCGC E-mail Newsletters

Subscribe: Click to learn more about the newsletter
| Weekly
| Monthly
|Monthly
| Weekly

Survey
Which of the following business challenge poses the greatest threat to your company?
Building a sustainable pipeline of products
Attracting a skilled workforce
Obtaining/maintaining adequate financing
Regulatory compliance
Building a sustainable pipeline of products
30%
Attracting a skilled workforce
27%
Obtaining/maintaining adequate financing
14%
Regulatory compliance
30%
View Results
Eric Langer Outsourcing Outlook Eric LangerBiopharma Outsourcing Activities Update
Cynthia Challener, PhD Ingredients Insider Cynthia Challener, PhDAppropriate Process Design Critical for Commercial Manufacture of Highly Potent APIs
Jill Wechsler Regulatory Watch Jill Wechsler FDA and Manufacturers Seek a More Secure Drug Supply Chain
Sean Milmo European Regulatory WatcchSean MilmoQuality by Design?Bridging the Gap between Concept and Implementation
Medicare Payment Data Raises Questions About Drug Costs
FDA Wants You!
A New Strategy to Tackle Antibiotic Resistance
Drug-Diagnostic Development Stymied by Payer Concerns
Obama Administration Halts Attack on Medicare Drug Plans
Source: Pharmaceutical Technology,
Click here