Supply Chain Pain

Published on: 
Pharmaceutical Technology, Pharmaceutical Technology-05-02-2011, Volume 35, Issue 5

Lessons from the earthquake in Japan show the vulnerability of the bio/pharma supply chain.

The tragic earthquake and tsunami in Japan in March rocketed supply-chain issues to a prominent position. Even the most sophisticated supply-chain managers were caught off guard by the event, which caused the shutdown of many manufacturing sites due to earthquake damage or power-supply interruptions.

Jim Miller

What is striking about the impact of the Japan earthquake on the supply-chain is the widespread production disruptions caused by supply interruptions of simple components. Automobile manufacturers were forced to shut down manufacturing operations at plants around the world due to component shortages. For example, Ford halted shipments of some cars just because of a shortage of certain paint pigments. Perhaps most famously, production of Apple's iPad2 was threatened by the shutdown of a supplier in northeastern Japan making a connector costing just a few cents.

The automobile and electronics industries are known for their supply-chain sophistication, including their ability to source components globally and have them delivered just-in-time to the manufacturing floor. The fact that their production would be disrupted by such minor components speaks to just how complex effective supply-chain management really is.

Bio/pharma industry vulnerability

Reports so far suggest that the bio/pharmaceutical supply-chain has only been marginally affected by the events in Japan. We have heard of only two interruptions. One was from a supplier of glycine, an ingredient in some common solid-dosage products, which indicated that production may be shut down for up to 24 months. We also heard of disruptions in some supplies of gelatin used in softgel capsules, for which alternative suppliers are readily available.

Nevertheless, the bio/pharmaceutical industry has not been without its own supply-chain difficulties in recent months. A major fire destroyed a warehouse attached to Catalent's commercial packaging facility in Corby, United Kingdom, and problems stemming from delamination in glass vials resulted in a number of injectable products being recalled from the market.

The pharmaceutical industry has done surprisingly little to protect itself from supply-chain interruptions. PharmSource recently conducted a survey about a widely used component for solid-dosage drugs, which typically requires preformulation compatibility testing, and found that few companies have exhibited the foresight to qualify second or third suppliers.

For component-assembly industries, such as automobiles or electronics that are relatively unregulated, the interruption in the supply of a minor component will be disruptive and relatively short-lived. In most cases, it could be a matter of weeks to redesign the component or have substitute suppliers step in for secondary supply. In the bio/pharmaceutical industry, however, the long-term interruption of a minor component could be catastrophic. Even a relatively minor excipient can cause changes in a product's characteristics, thereby requiring full preformulation analysis, stability testing, and testing of production batches. Add to that the supplier qualification and regulatory-filing requirements, and the production time lost can be considerable.

This lack of advanced planning by bio/pharmaceutical companies is surprising because the potential costs are so high. An extended period of lost production means lost sales and loss of market share to competitors that might never be regained.

Inadequate supply-chain practices

The bio/pharmaceutical industry's lack of supply-chain sophistication spans the entire length of the chain, from input sourcing, through production and inventory management, to distribution. At the front end of the chain, we need only be reminded of the heparin disaster of a few years ago to appreciate the weaknesses in quality assurance and supplier management for key inputs. At the distribution end of the supply, the bio/pharmaceutical industry has been under attack regarding counterfeiting and security of supply. A recent article in Fortune magazine recounted last year's theft of $75 million of finished drug product from an Eli Lilly warehouse in Enfield, Connecticut (1). The article highlighted the lax security at the warehouse, including failure to monitor security cameras that could have caught the theft while it was taking place (1).

Supply-chain management weakness also can be seen in the way the industry manages its inventories. On average, the global bio/pharmaceutical companies turn their inventories a little more than twice a year. They typically have inventory on hand equivalent to about 180 days' worth of sale. By contrast, a best-practice consumer products firm, such as Procter and Gamble, turns its inventory about six times a year and has about 60 days' worth of inventory on hand. As global bio/pharmaceutical companies are trying to maximize their cash-on-hand to help them weather the patent cliff and take advantage of licensing and acquisition opportunities, keeping so much cash tied up in inventory is a real competitive disadvantage.

Opportunity for contract services

The supply-chain management challenges facing the bio/pharmaceutical industry represent a major opportunity for providers of contract services, especially those in manufacturing (i.e., contract manufacturing organizations [CMOs]) and packaging. Because of their critical position relative to both the upstream and downstream segments of the supply-chain, CMOs and packagers are well positioned to help bio/pharmaceutical companies manage their risk and squeeze cost and inventory out of the system.

We have seen isolated instances of contract services providers responding to supply-chain management opportunity (e.g., Patheon's recent efforts to promote its services as a backup source of supply and Almac's short-run packaging services). We've also seen some major providers of third-party logistics services (3PL), such as UPS, DHL and FedEx, make greater efforts to address the bio/pharmaceutical industry.

However, the big opportunity will come when service providers, especially CMOs, figure out how to increase the flexibility and responsiveness of their own operations. For instance, every day that a CMO can knock off the manufacturing schedule lock-in requirement from its traditional three months can save its bio/pharmaceutical company clients millions of dollars in cash tied up in inventory. Further, the internal process changes necessary to achieve those scheduling improvements are likely to deliver substantial cost savings and increased throughput. Given that most CMOs operate well below full capacity, such flexibility should be attainable.

CMOs have traditionally focused on additions to processing technologies, equipment and gain-to-gain incremental volume. Given the supply-chain challenges facing the bio/pharmaceutical industry, a focus on operations excellence in the context of supply-chain management is likely to yield greater performance for both the client and CMO and yield market share gains going forward.

Jim Miller is president of PharmSource Information Services, Inc., and publisher of Bio/Pharmaceutical Outsourcing Report, tel. 703.383.4903, fax 703.383.4905, info@pharmsource.com, www.pharmsource.com.

Reference

1. K. Eban, Fortune, Mar. 31, 2011, http://features.blogs.fortune.cnn.com/2011/03/31/drug-theft-goes-big/, accessed Apr. 11, 2010.